news-uk

Truro Tidal Gates Prepared for Action

In a significant step toward flood protection, Truro has updated its flood defense system, securing 185 properties for the next three decades. This initiative is centered on the newly refurbished tidal gates, forming a vital component of the city’s flood risk management strategy.

Project Overview and Timeline

The refurbishment project commenced in April 2024, involving the replacement of outdated gates that could no longer meet performance standards. The installation was completed by August 2024, utilizing a 400-tonne crane during optimal conditions that aligned with the spring tides.

Emergency Preparedness During Construction

The project demonstrated robust emergency planning when unanticipated tidal surges occurred. Temporary flood barriers, known as stoplogs, were effectively deployed for the first time at Truro. This response not only protected the city from flooding but also confirmed the Environment Agency’s flood protection measures’ effectiveness.

Flood Defense System Enhancements

The newly installed gates are strategically designed to close during high spring tides and storm surges. This will ensure reliable protection against flooding for many years. Andrew Houghton, operations manager at the Environment Agency, emphasized the significant investment in Truro’s flood resilience, highlighting the enhanced reliability of the new flood defense system.

Community Benefits from Infrastructure Projects

One unexpected benefit of the project was the relocation of the old barrier control room to Perranporth Cricket Club. This facility has been renovated into a pavilion, adding changing amenities and supporting the growth of female cricket in the community.

Future Flood Risk Management Initiatives

The tidal barrier project is part of a broader effort to enhance Truro’s flood defenses in response to increasing climate change risks. Additional upgrades at the Idless Flood Storage Reservoir on the River Allen are nearing completion, set to become operational by December 2025. These upgrades aim to improve the dam’s resilience during severe weather events.

Community Preparedness and Initiatives

In July 2025, the Environment Agency conducted successful emergency pump tests at New Mills Dam flood storage reservoir to demonstrate their rapid response capabilities. Further training and exercises were completed in September 2025, focusing on best practices in compliance with reservoir safety legislation.

Flood Action Week and Public Awareness

This announcement coincided with Flood Action Week, an initiative by the Environment Agency aimed at raising awareness about flood risks across England. Climate change is causing increasingly severe weather patterns, with the Met Office predicting a wetter than average autumn. Approximately 6.3 million homes and businesses in England are now at risk of flooding from various sources.

Taking Action Against Flood Risks

  • Check your flood risk status.
  • Stay informed about flood warnings.
  • Develop a personal action plan.
  • Consider installing flood resilience measures for your property.

For more guidance on flood preparedness, visit gov.uk/prepare-for-flooding.