OC Transpo to Launch East LRT Extension by July

The east extension of the Light Rail Transit (LRT) system by OC Transpo is slated to begin service by the end of June 2024. Interim General Manager Troy Charter has confirmed that preparations are on track for a public service launch in the second quarter. The project has achieved a significant milestone known as “substantial completion,” although challenges with the number of operational train cars have raised concerns.
Current Challenges and Solutions
OC Transpo faces a shortage of train cars, with only 21 out of the required 46 available for daily operations due to ongoing mechanical issues. These issues stem from a malfunctioning bearing component affecting car axles, which has restricted the operational fleet.
- Current operational trains: 21
- Required for testing: 46
Alta Vista Councillor Marty Carr expressed the need for OC Transpo to increase the number of functioning trains to restore public confidence. OC Transpo is working with its contractor and technical teams to manage and replace malfunctioning components known as cartridge bearing assemblies. Charter acknowledged that availability of these components is limited and cannot be purchased readily.
Behind-the-Scenes Improvements
Chief Safety Officer Sabrina Pasian provided an update indicating progress in addressing the mechanical issues. OC Transpo is collaborating with its maintenance contractor, RTG, and the train manufacturer, Alstom, to explore revisions to the current operational guidelines, particularly the 100,000-kilometre limit on axle usage.
Proposed solutions include enhanced monitoring techniques such as acoustic and vibration assessments to identify potential bearing failures preemptively. The immediate goal is to restore regular service on the existing Line 1 between Blair and Tunney’s Pasture stations. Afterward, efforts will focus on increasing the fleet’s operational capacity to enable trial runs for the east extension.
West Extension Update
In addition to the east extension, updates were provided regarding the west extension to Algonquin and Moodie stations. Rail construction director Richard Holder announced a delay, with the projected handover of the system to the city now set for the second quarter of next year, approximately six months later than previously anticipated.
- Original handover schedule: Fall 2024
- Revised handover date: Q2 2025
Concerns have been raised regarding the increasing density of new apartment developments along the western route without adequate transit infrastructure. Kitchissippi Councillor Jeff Leiper highlighted the implications for residents who will rely on LRT service to mitigate congestion in the area.
Conclusion
OC Transpo is actively working on resolving car shortages and mechanical issues while preparing for the launch of the east LRT extension by July 2024. Continuous updates and engagement with stakeholders will be crucial as the agency navigates the complexities posed by construction delays and operational challenges.




